V&V Work Plan
🔴 BEHIND SCHEDULE. Original deadline was 2026-06-30 — now past. As of 2026-07-01, all active filters below are OVERDUE and not yet started. This is a recovery schedule showing the earliest realistic completion, not the committed date.
- Recovery assumptions: start Wed 2026-07-01
- weekends off
- Fri 2026-07-03 excluded (Independence Day observed)
- engineers work queues sequentially, all in parallel
- 4 working days per filter, except imikejackson at 2 days/filter (~2× throughput)
- 5 filters already have PRs in review and are excluded from the recompute.
- Earliest projected completion: 2026-07-23, driven by mmarinebluequartz / jduffeybq / nyoungbq (4 filters × 4 days = 16 working days each). - imikejackson clears 7 filters by 2026-07-21
- This is ~3.5 weeks past the 2026-06-30 deadline.
Each item: C++ class — display name · plugin · start→due · PR number. Check the box and fill the PR number as each lands.
PR Currently Submitted (in review — excluded from schedule)
Work Queue (rack & stack)
mmarinebluequartz — 4 filters @ 4 days · finishes 2026-07-23
imikejackson — 7 filters @ 2 days · finishes 2026-07-21
jduffeybq — 4 filters @ 4 days · finishes 2026-07-23
nyoungbq — 4 filters @ 4 days · finishes 2026-07-23
Workload by Engineer
| Engineer |
Active |
Rate |
Finishes |
Plugins touched |
| mmarinebluequartz |
4 |
4 d/filter |
2026-07-23 |
SimplnxCore (3), OrientationAnalysis (1) |
| imikejackson |
7 |
2 d/filter |
2026-07-21 |
OrientationAnalysis (4), SimplnxCore (2), SimplnxReview (1) |
| jduffeybq |
4 |
4 d/filter |
2026-07-23 |
SimplnxCore (2), OrientationAnalysis (1), ITKImageProcessing (1) |
| nyoungbq |
4 |
4 d/filter |
2026-07-23 |
SimplnxCore (4) |
| PR in review |
5 |
— |
— |
OrientationAnalysis (4), SimplnxCore (1) |
Open Items / Data Issues
- 🔴 Past deadline (2026-06-30). Every active filter is overdue. The dates above are a recovery projection, not a restored commitment.
- imikejackson runs at 2× throughput (2 days/filter)
— that's why a 7-filter queue still finishes first (2026-07-21). If that rate slips to the standard 4 days, Jackson becomes the critical path at ~2026-08-14.
MergeColoniesFilter lives in an external plugin (SimplnxReview at ../DREAM3D_Plugins/SimplnxReview), not the main simplnx repo. Its GitHub issue/PR will still be tracked here unless you want it elsewhere.
Options to Recover Time
Critical path is the three 4-day engineers finishing 2026-07-23 (16 working days). To pull that in:
- Shorten cadence on simple filters — writers/rotations (e.g.
WriteDREAM3DFilter, ITKImageWriterFilter) may be 2–3 days rather than 4; front-load the heavy ones.
V&V Work Plan
Each item: C++ class — display name · plugin · start→due · PR number. Check the box and fill the PR number as each lands.
PR Currently Submitted (in review — excluded from schedule)
Work Queue (rack & stack)
mmarinebluequartz — 4 filters @ 4 days · finishes 2026-07-23
imikejackson — 7 filters @ 2 days · finishes 2026-07-21
jduffeybq — 4 filters @ 4 days · finishes 2026-07-23
nyoungbq — 4 filters @ 4 days · finishes 2026-07-23
Workload by Engineer
Open Items / Data Issues
— that's why a 7-filter queue still finishes first (2026-07-21). If that rate slips to the standard 4 days, Jackson becomes the critical path at ~2026-08-14.
MergeColoniesFilterlives in an external plugin (SimplnxReview at../DREAM3D_Plugins/SimplnxReview), not the main simplnx repo. Its GitHub issue/PR will still be tracked here unless you want it elsewhere.Options to Recover Time
Critical path is the three 4-day engineers finishing 2026-07-23 (16 working days). To pull that in:
WriteDREAM3DFilter,ITKImageWriterFilter) may be 2–3 days rather than 4; front-load the heavy ones.